Emmett Township Construction Update

Receive the most updated information from the Calhoun County Road Department
Sign up for Textcaster updates here

The Emmett Township Local Road Project is in its second year, with construction ongoing throughout the township. There are two ways to explore this project. 

Click here for an interactive map of this project. 
Emmett Township Local Road Project 
Weekly Project Updates

PROJECT UPDATE NOVEMBER 17, 2021: 

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment at staked locations

Contractors will be on Drive N (Raymond to Wattles), D Drive N (9 Mile to 11 Mile), and E Drive N (Beadle Lake Rd to 9 Mile) doing the following items of work:
- Topsoil behind HMA curbs

Slope Restoration efforts are on-going for all streets with completed base and top course paving. 
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving. 
Punch List Items are on-going throughout the Township.

This will be the final Emmett LRP update for the year. Several minor punch-list items will continue to be completed, however, all major paving items are either completed or scheduled for the 2022 construction season. Just over 11 miles of paving are currently left on the contract.

PROJECT UPDATE NOVEMEBR 8, 2021:

Contractors will be on Strongwood Ave, Robins Ln, D Drive N (6.5 to BLR), I Drive N, Southbrook, Beavers Ridge, Council Crest Cir, and Kistler Rd doing the following items of work:
- Misc. Pavement and Driveway Fixes
Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Shouldering

Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.

PROJECT UPDATE NOVEMBER 1, 2021: 
Contractors will be on Strongwood Ave, Robins Ln, D Drive N (6.5 to BLR), Council Crest Cir, and Kistler Rd doing the following items of work:
- Misc. Pavement and Driveway Fixes

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
-Shouldering

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Shouldering

Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.

PROJECT UPDATE OCTOBER 25, 2021:

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Top Course Paving
- Shouldering

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Shouldering

Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.

PROJECT UPDATE OCTOBER 18, 2021:

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Finish Grading
- Removing Driveway Approaches
- Paving Base Course

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Shouldering

Tree Work will be continuing in the Presidents’ Subdivision.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.
All additional roads not yet completed will be reconstructed in 2022.

PROJECT UPDATE OCTOBER 11, 2021:

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Finish Grading
- Removing Driveway Approaches

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Drainage Structure Adjustments
- Shouldering

Tree Work will be continuing in the Presidents’ Subdivision.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.

PROJECT UPDATE OCTOBER 4, 2021:

Contractors will be on D Drive N between 9 Mile Rd and 11 Mile Rd doing the following items of work:
- Curb and Gutter Replacement
- Grading/Rolling in preparation for paving
- Aggregate Base Additions

Contractors will be on E Drive N between Beadle Lake Rd and 9 Mile Rd doing the following items of work:
- Top Course Approach Paving
- Drainage Structure Adjustments
- Shouldering

Contractors will be in Parkshore Subdivision doing the following items of work:
- Drainage Structure Adjustments

Tree Work will be continuing in Bach/Hoover and Presidents’ Subdivisions.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Punch List Items are on-going throughout the Township.

PROJECT UPDATE SEPTEMBER  28, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Top Course Paving (Alden, Nelson, Grenville, Illinois, Euclid, Richmond)

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Culvert Removal
- Curb and Gutter Replacement
- Grading/Rolling in preparation for paving
- Aggregate Base Additions

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Curb and Gutter Replacements
- Top Course Paving

Contractors will be on Council Crest doing the following items of work:
- Drainage Structure Adjustments

Contractors will be in Parkshore Subdivision doing the following items of work:
- Drainage Structure Adjustments

Tree Work will be continuing in Bach/Hoover Subdivision.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.
Pavement Markings are on-going for the 1st and 2nd applications.

PROJECT UPDATE SEPTEMBER 13, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Top Course Paving (Alden, Nelson, Grenville, Illinois, Euclid, Richmond)

Contractors will be on Kimball Pines Trail doing the following items of work:
- Base Course Paving
- Top Course Paving

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Culvert Replacements
- Pulverization
- Grading/Rolling in preparation for paving
- Aggregate Base Additions

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Grading/Rolling in preparation for paving
- Embankment Additions
- Base Course Paving

Contractors will be on Council Crest doing the following items of work:
- Top Course Paving
- Driveway Gravel
- Drainage Structure Adjustments

Contractors will be in Parkshore Subdivision doing the following items of work:
- Top Course Paving
- Drainage Structure Adjustments

Tree Work will be continuing on 6.5 Mile Rd (B Drive N to Township Line) and D Drive N (near 10.5 Mile).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT  UPDATE SEPTEMBER  7, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Top Course Paving (Alden, Nelson, Grenville, Illinois, Euclid, Richmond)

Contractors will be on Woodland Park, Southshore Dr, and Auburn St doing the following items of work:
- Chip Seal Sweeping
- Fog Sealing

Contractors will be on Ott Trailhead Parking Lot and Kimball Pines Trail doing the following items of work:
- Aggregate Base Conditioning
- HMA Approach Removals
- Base Course Paving

Contractors will be on G Drive N (Wattles to Dead End), Kistler Rd, and Beadle Lake Dr doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (Kistler Rd, Beadle Lake Drive)

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Culvert Replacements

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Curb and Leaching Basin Installation (9 Mile Rd)
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on Council Crest doing the following items of work:
- Top Course Paving
- Driveway Gravel
- Drainage Structure Adjustments

Contractors will be in Parkshore Subdivision doing the following items of work:
- Aggregate Base Dig-outs
- Base Course Patching
- Top Course Paving
- Driveway Gravel
- Drainage Structure Adjustments

Tree Work will be continuing on 6.5 Mile Rd (B Drive N to Township Line) and D Drive N (near 10.5 Mile).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE AUGUST 30, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Drainage Fixes (Nelson, Grenville)
- Top Course Paving (Alden, Nelson, Grenville, Illinois, Euclid, Richmond)

Contractors will be on 8.5 Mile Rd doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments

Contractors will be on G Drive N (Wattles to Dead End), Kistler Rd, and Beadle Lake Dr doing the following items of work:
- Top Course Paving
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Embankment Additions

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile) doing the following items of work:
- Superelevation Grading
- Aggregate Base Additions
- Curb/Leaching Basin Installation (9 Mile Rd)
- Grading/Rolling in preparation for paving

Contractors will be on Council Crest doing the following items of work:
- Top Course Paving
- Driveway Gravel
- Drainage Structure Adjustments

Contractors will be in Parkshore Subdivision doing the following items of work:
- Grading/Rolling in preparation for paving
- Base Course Paving

Tree Work will be continuing on E Drive N (6.5 Mile to Beadle Lake Road).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE AUGUST 24, 2021:

Contractors will be in the Alden Ave E. subdivisions doing the following items of work:
- Drainage Fixes (Nelson)
- Aggregate Base Conditioning
- Base Course Paving (Euclid, Alden Ave E, Richmond)
- Top Course Paving (Inn, Marjorie, Nelson, Illinois)

Contractors will be on 8.5 Mile Rd doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)
- Culvert Ditching

Contractors will be on Kistler Rd and Beadle Lake Dr. doing the following items of work:
- Culvert Drainage Inspection
- Top Course Paving

Contractors will be on G Drive N (Raymond to Wattles/Wattles to Dead End), E River Rd, E Drive N (12 Mile to gravel) doing the following items of work:
- Driveway Removals
- Butt Joint Removals
- Grading/Rolling in preparation for paving
- Base Course Paving
- Top Course Paving

Contractors will be on E Drive N (Beadle Lk Rd to 9 Mile), Council Crest Subdivision, and Parkshore Subdivision doing the following items of work:
- Aggregate Base Conditioning (Parkshore Sub)
- Aggregate Base Additions (E Drive N, Council Crest Sub)
- Curb Replacements (Parkshore Sub)
- Grading/Rolling in preparation for paving
- Base Course Paving (Parkshore and Council Crest Subs)

Contractors will be on D Drive N (9 Mile to 11 Mile) doing the following items of work:
- Machine Grading
- Pulverization
- Grading/Rolling in preparation for paving

Contractors will be in Flowerwood Subdivision doing the following items of work:
- Road Surface Milling
- Aggregate Base Conditioning

Tree Work will be continuing on E Drive N (6.5 Mile to Beadle Lake Road).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE AUGUST 17, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Curb Replacements (Illinois, Euclid, Alden Ave E)
- Drainage Fixes (Nelson/Grenville)
- Aggregate Base Conditioning
- Base Course Paving (Illinois, Euclid, Alden Ave E)
- Top Course Paving (Inn, Marjorie, Nelson)

Contractors will be on Beavers Ridge, Trappers Ridge, Church St, Battle Creek St, Ackerson doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Harper Crossing, W Armour Ln, Creekside, Beadle Lake Dr, 8.5 Mile Rd doing the following items of work:
 - Top Course Paving

Contractors will be on G Drive N (Raymond to Wattles/Wattles to Dead End), E River Rd, E Drive N (12 Mile to gravel) doing the following items of work:
- Driveway Removals
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on Council Crest Subdivision and Parkshore Subdivision doing the following items of work:
- Road Surface Milling
- Aggregate Base Conditioning
- Removal of sand road base & adding gravel
- Sewer Structure Adjustment

Tree Work will be continuing on D Drive N (8.5 Mile to 11 Mile).
Slope Restoration efforts are on-going for all streets with completed base and top course paving. 
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE AUGUST 10, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Curb Replacements (Illinois, Euclid, Alden Ave E)
- Drainage Fixes (Nelson)
- Aggregate Base Conditioning
- Base Course Paving (Illinois, Euclid, Alden Ave E)
- Top Course Paving (Inn, Marjorie, Nelson)

Contractors will be on Beavers Ridge, Trappers Ridge, Church St, Battle Creek St, Ackerson doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Harper Crossing, W Armour Ln, Creekside, Beadle Lake Dr, 8.5 Mile Rd doing the following items of work:
 - Top Course Paving

Contractors will be on G Drive N (Raymond to Wattles/Wattles to Dead End), E River Rd, E Drive N (12 Mile to gravel) doing the following items of work:
- Driveway Removals
- Culvert Installation
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on Council Crest Subdivision and Parkshore Subdivision doing the following items of work:
- Road Surface Milling
- Aggregate Base Conditioning
- Curb Replacements

Tree Work will be continuing on D Drive N (8.5 Mile to 11 Mile).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE AUGUST 2, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Curb Replacements
- Road Surface Milling (Euclid, Illinois St, Alden Ave E)
- Aggregate Base Conditioning
- Base Course Paving
- Top Course Paving (Inn, Marjorie, Nelson)

Contractors will be on Beavers Ridge, Trappers Ridge, Sherry Lane, Tammy Ann Cir, Harper Hill, Berry Hill, Southbrook, Singletree, Church St, Battle Creek St, Ackerson doing the following items of work:
- Driveway Gravel  
- Drainage Structure Adjustments (if applicable)

Contractors will be on Harper Crossing, Kistler/Beadle Lake Dr Subdivision doing the following items of work:
- Top Course Paving

Contractors will be on 8.5 Mile Rd, Creekside, W. Armour, and E Drive N (12 Mile to gravel) doing the following items of work:
- Driveway Removals
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on G Drive N (Raymond to Wattles/Wattles to Dead End) and E River Rd doing the following items of work:
- Machine Grading
- Pulverizing (only G Drive N from Raymond to Wattles/Wattles to Dead End)
- Driveway Removals
- Installing Culverts
- Grading/Rolling in preparation for paving

Tree Work will be continuing on E Drive N (12 Mile to gravel), E Drive N (BLR to 9 Mile), D Drive N.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE JULY 26, 2021:

Contractors will be in the Alden Ave E. Subdivision doing the following items of work:
- Curb Replacements
- Road Surface Milling (Illinois St)
- Aggregate Base Conditioning
- Base Course Paving

Contractors will be on Beavers Ridge, Sherry Lane, Tammy Ann Cir, Harper Hill, Dundee Dr, Southbrook, Singletree, Allison and Robins Lns doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Hoyt and Wyncrest installing the following items of work:
- Shoulder Drainage Material

Contractors will be on Berry Hill, Trappers Ridge, Ackerson Dr, Church St, Battle Creek St, and Kistler/Beadle Lake Dr Subdivision doing the following items of work:
- Top Course Paving

Contractors will be on Creekside, W. Armour, Harpers Crossing, and E Drive N (12 Mile to gravel) doing the following items of work:
- Driveway Removals
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Machine Grading
- Pulverizing (only G Drive N from Raymond to E River Rd)
- Driveway Removals
- Installing Culverts
- Grading/Rolling in preparation for paving

Tree Work will be continuing on E Drive N (12 Mile to gravel), E Drive N (BLR to 9 Mile), Flowerwood Dr., G Drive N (E of Wattles).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.
Mailbox Adjustment efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE JULY 19, 2021:

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Curb Replacements
- Road Surface Milling

Contractors will be on Sherry Lane, Tammy Ann Cir, Harper Hill, Dundee Dr, Southbrook, Singletree, Allison and Robins Lns doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Hoyt and Wyncrest installing the following items of work:
- Shoulder Drainage Material

Contractors will be on Berry Hill, Trappers Ridge, Ackerson Dr, Church St, Battle Creek St, E Drive N (12 to gravel) doing the following items of work:
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on Beavers Ridge and Kistler/Beadle Lake Dr Subdivision performing the following items of work:
- Top Course Paving

Contractors will be on Creekside, W. Armour, Harpers Crossing doing the following items of work:
- Pulverizing
- Driveway Removals
- Grading/Rolling in preparation for paving

Contractors will be on G Drive N (Raymond to Wattles) and E River Rd doing the following items of work:
- Machine Grading
- Installing Culverts
- Pulverizing (only G Drive N from Raymond to E River Rd)
- Driveway Removals
- Grading/Rolling in preparation for paving

Tree Work will be continuing on E Drive N (BLR to 9 Mile), Flowerwood Dr, and G Drive N (E of Wattles).
Slope Restoration efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE JULY 12, 2021:

Contractors will be in the Alden Ave W. Subdivisions doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work:
- Curb Replacements
- Road Surface Milling

Contractors will be on Dundee Dr, Southbrook, Singletree, Allison and Robins Lanes doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Berry Hill, Sherry Lane, and Tammy Ann Cir doing the following items of work:
- Grading/Rolling in preparation for paving (Berry Hill)
- Base/Top Course Paving

Contractors will be on Ackerson Dr., Church St, Battle Creek St, E Drive N (12 to gravel) doing the following items of work:
- Driveway Removals
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be in Kistler/Beadle Lake Dr. Subdivision performing the following items of work:
- Grading/Rolling in preparation for paving
- Base/Top Course Paving

Contractors will be on Hoyt and Wyncrest installing the following items of work:
- Shoulder Drainage Material

Contractors will be on Trappers Ridge, Beavers Ridge doing the following items of work:
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be on Creekside, W. Armour, Harpers Crossing doing the following items of work:
- Driveway Removals
- Pulverizing
- Grading/Rolling in preparation for paving

Tree Work will be continuing on Creekside, W. Armour, and Harpers Crossing and the Kistler/Beadle Lake Dr. Subdivision.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE JULY 6, 2021:

Contractors will be in the Alden Ave W. Subdivisions doing the following items of work:
-Subgrade Undercutting (Taft)
-Top Course Paving
- Structure Adjustments
- Driveway Gravel

Contractors will be in the Alden Ave E. Subdivisions doing the following items of work
- Curb Replacements
- Road Surface Milling

Contractors will be on Dundee Dr., Southbrook, Singletree, Allison and Robins Lns doing the following items of work:
- Driveway Gravel   
- Drainage Structure Adjustments (if applicable)

Contractors will be on Berry Hill, Sherry Lane, and Tammy Ann Cir doing the following items of work:
- Grading/Rolling in preparation for paving (Berry Hill)
 - Culvert Installation (Berry Hill)
- Cold Milling (Sherry Ln)
- Base/Top Course Paving

Contractors will be in Kistler/Beadle Lake Dr.. Subdivision performing the following items of work:
- Driveway Removals
- Grading/Rolling in preparation for paving
- Culvert Installations on Beadle Lake Drive
- Ditching
- Base Course Paving

Contractors will be on Hoyt and Wyncrest installing the following items of work:
- Slope Restoration
- Shoulder Drainage Material

Contractors will be on Trappers Ridge, Beavers Ridge, Creekside, W. Armour, Harpers Crossing doing the following items of work:
- Machine Grading
- Driveway Removals
- Pulverizing
- Grading/Rolling in preparation for paving
- Base Course Paving

Tree Work will be continuing on Creekside, W. Armour, and Harpers Crossing and the Kistler/Beadle Lake Dr. subdivision.
Slope Restoration efforts are on-going for all streets with completed base and top course paving.

PROJECT UPDATE JUNE 28, 2021:
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Finishing Slope Restoration

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
-Grading/Rolling in preparation for paving
- Curb Replacements
- Road Surface Milling
 
Contractors will be on Southbrook, Dundee Dr, Berry Hill, Sherry Lane, and Tammy Ann Cir doing the following items of work:
- Grading/Rolling in preparation for paving
-  Culvert Installation (if applicable)
- Base/Top Course Paving
 
Contactors will be on Allison and Robins Lns doing the following items of work:
- Driveway Gravel    
- Drainage Structure Adjustments
- Slope Restoration
 
Contractors will be in Kistler/Beadle Lake Dr Subdivision performing the following items of work:
- Finishing Pulverizing
- Grading/Compacting
- Pump/Drainage Basin install on Kistler Rd

Contactors will be on Hoyt and Wyncrest doing the following items of work:
-  Butt Joint and Driveway Milling
- Overlay Paving

Tree Work will be continuing on 8.5 Mile Rd and the Kistler/Beadle Lake Dr Subdivision.

PROJECT UPDATE JUNE 21, 2021:

Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Slope restoration in Jameson Subdivisions
- Continuing Driveway Gravel

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be on Southbrook & and Berry Hill doing the following items of work:
- Grading/Rolling in preparation for paving
-Culvert Installation
-Base/Top Course Paving

Contactors will be on Robins Ln and Dundee Dr doing the following items of work:
- Base/Top Course Paving

Contractors will be in Kistler/Beadle lake Dr Subdivision performing the following items of work:
- Pulverizing
- Grading/Compacting
- Drainage basin install on Kistler Rd

Tree Work will be continuing on 8.5 Mile Rd and D Drive N

PROJECT UPDATE JUNE 14, 2021:
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Paving  Top Course in Jameson Subdivisions
- Continuing Driveway Gravel
- Continuing Slope Restoration

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be on Southbrook, Singletree, Harper Hill, and Berry Hill doing the following items of work:
- Grading/Rolling in preparation for paving
- Culvert Installation
- Base/Top Course Paving

Contactors will be on Allison Ln, Robins Ln, and Dundee Drive doing the following items of work:
- Pulverizing
- Grading/Rolling in preparation for paving
- Removing Approaches

Contractors will be on Lourim Ct and Cornwell St doing the following items of work:
- Paving Top Course
- Slope Restoration

Tree Work will be continuing on 8 1/2 Mile Road between C Drive N and D Drive N between the hours of 9:00 am and 2:00 pm.

PROJECT UPDATE JUNE 7, 2021: 

Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Paving Top Course in Jameson Subdivisions
- Continuing Driveway Gravel
- Continuing Slope Restoration
- Tree Work (Vass Ave)

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be on Southbrook, Singletree, Harper Hill, and Berry Hill doing the following items of work:
- Grading/Rolling in preparation for paving
- Base Course Paving

Contactors will be on Allison Ln, Robins Ln, and Dundee Dr doing the following items of work:
- Pulverizing
- Grading/Rolling in preparation for paving
- Removing Approaches

Contractors will be on Lourim Ct and Cornwell St doing the following items of work:
- Paving Top Course
- Slope Restoration

Tree Work will be continuing on 8.5 Mile Rd between B Drive N and D Drive N between the hours of 9a and 2p

PROJECT UPDATE JUNE 1, 2021: 
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Paving Top Course in Jameson Subdivisions
- Continuing Driveway Gravel
- Continuing Slope Restoration

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Tree Work (Euclid)
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be in the Woodland Beach Subdivision doing the following items of work:
- Slope Restoration

Contractors will be in Southbrook, Singletree, Harper Hill, and Berry Hill subdivisions doing the following items of work:
- Removing Approaches
- Grading/Rolling in preparation for paving

Contactors will be in subdivisions off of 8.5 Mile doing the following items of work:
- Pulverizing
- Grading/Rolling in preparation for paving
- Removing Approaches

Contractors will be in Lourim Ct and Cornwell St area doing the following items of work:
- Paving Top Course
- Concrete Approach Installation
- Curb Replacements
- Slope Restoration

Tree Work will be continuing on 8.5 Mile Rd between B Drive N and D Drive N between the hours of 9a and 2p


PROJECT UPDATE MAY 24, 2021
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Paving Top Course in Electric/Jameson Subdivisions
- Continuing Driveway Gravel
- Continuing Slope Restoration

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Tree Trimming (Alden Ave W)
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be in the Woodland Beach Subdivision doing the following items of work:
- Overlay Paving Corrections
- Slope Restoration

Contractors will be in Southbrook, Singletree, Harper Hill, and Berry Hill subdivisions doing the following items of work:
- Machine Grading
- Removing Approaches
- Pulverizing
- Grading/Rolling in preparation for paving

Contractors will be in Lourim Ct and Cornwell St area doing the following items of work:
- Paving Top Course
- Concrete Approach Installation
- Curb Replacements
- Slope Restoration

Tree Work will be continuing on 8.5 Mile Rd between B Drive N and D Drive N between the hours of 9a and 2p


PROJECT UPDATE MAY 17, 2021: 
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Grading/Compacting Aggregate Base in Jameson Sub
- Paving Top Course in Electric Sub
- Paving Base Course in Jameson Sub
- Driveway Gravel
- Slope Restoration

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Grading/Rolling in preparation for paving
- Curb Replacements
- Drainage Structure Installation on Alden Ave W.
- Various Added Tree Work

Contractors will be in the Woodland Beach Subdivision doing the following items of work:
- Overlay Paving Corrections
- Slope Restoration

Tree Work will be moving to 8.5 Mile Rd between B Drive N and D Drive N


PROJECT UPDATE MAY 3, 2021: 
Contractors are in the subdivisions off of Raymond Road doing the following items of work:
- Adding Aggregate Base
- Grading/Rolling in preparation for paving
- Base Course Paving

Contractors will be in the Alden Ave W. and E. Subdivisions doing the following items of work:
- Grading/Rolling in preparation for paving
- Curb Replacements

Contractors will be in the Woodland Beach Subdivision doing the following items of work:
- Overlay Paving
- Slope Restoration
- Drainage Structure Adjustments

Tree Removals and Trimming along E Dr N between Beadle Lake Road and Wattles Road will be wrapping up