Emmett Township Construction Update

Receive the most updated information from the Calhoun County Road Department
Sign up for Textcaster updates here

Explore the Project
Phase 1 (this year)
Phase 2
Phase 3

Week of October 26

The following roads have had paving completed and are awaiting restoration.

  • Fruin
  • Linn
  • Woodway
  • Pinewood
  • Pawnee
  • Cherokee
  • Marion
  • Auburn
  • Belton
  • L Drive N (Palmiter to Wheatfield)
  • Palmiter
  • N Princeton
  • Bradford/Rook subdivision
  • Harper Creek Dr
  • Anway Drive
  • D Drive N (6 ½ to Beadle Lk Rd)
  • Fern Beach
  • Hollison Beach
  • C Drive N (8 ½ to Beadle Lake Rd)

Tree cleanup will continue at these locations:

  • C Drive N (8 ½ to Beadle Lake Rd)
  • D Drive N (6 ½ to Beadle Lake Rd)
  • L Drive N (9 ½ to 11)
  • Bradford/Rook subdivision

A Lakeland crew will be going around (date TBD) milling/filling several driveways that need correction.

Hoffman Bros will continue working on mailbox adjustments in the area of Bradford and Olive subdivisions.

Week of October 19

The following roads have had paving completed and are awaiting restoration.

  • Fruin
  • Linn
  • Woodway
  • Pinewood
  • Pawnee
  • Cherokee
  • Marion
  • Auburn
  • Belton
  • L Drive N (Palmiter to Wheatfield)
  • Palmiter
  • N Princeton
  • Bradford/Rook subdivision
  • Harper Creek Dr
  • Anway Drive
  • D Drive N (6 ½ to Beadle Lk Rd)
  • Fern Beach
  • Hollison Beach
  • C Drive N (8 ½ to Beadle Lake Rd)

Tree cleanup will continue at these locations:

  • C Drive N (8 ½ to Beadle Lake Rd)
  • D Drive N (6 ½ to Beadle Lake Rd)
  • Bradford/Rook subdivision

A Lakeland crew will be going around (date TBD) milling/filling several driveways that need correction.

Hoffman Bros will continue working on mailbox adjustments in the area of 10 mile, Olive subdivision.

Week of October 12

The following roads have had paving completed and are awaiting restoration. 

  •  O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Ashley Ct
  • Overton
  • S River 
  • Fruin
  • Linn
  • Woodway
  • Pinewood
  • Pawnee
  • Cherokee
  • Marion
  • Auburn
  • L Drive N (Palmiter to Wheatfield)
  • Palmiter
  • N Princeton
  • Silver Street
  •  McCormick       
  • Belton    
  • Bradford/Rook subdivision
  • Harper Creek Dr
  • Anway Drive
  • D Drive N, from 6 ½ to Beadle Lk Rd
  • Lady Jessica Isle
  • Fern Beach
  • Hollison Beach
The base course has been paved on C Drive North with the top course to be paved in the coming days.  Tree clean up also continues on this road stretch between Beadle Lake Road and 8 1/2 Mile Road.  

We plan this week (possibly Tuesday) to have a Lakeland crew milling/filling a few driveways that need correction.

Contractors will also be working on mailbox adjustments in the area of 10 Mile Road and I Drive North. 

Week of October 5

The following roads have had paving completed and are awaiting restoration. 

  •  O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Ashley Ct
  • Overton
  • S River 
  • Fruin
  • Linn
  • Woodway
  • Pinewood
  • Pawnee
  • Cherokee
  • Marion
  • Auburn
  • L Drive N (Palmiter to Wheatfield)
  • Palmiter
  • N Princeton
  • Silver Street
  •  McCormick       
  • Belton    
  • Bradford/Rook subdivision
  • Harper Creek Dr
  • Anway Drive
  • D Drive N, from 6 ½ to Beadle Lk Rd
  • Lady Jessica Isle
  • Fern Beach
  • Hollison Beach

This road has had the base course of asphalt paved. The top course will be paved in the coming days.

  • C Drive N, from Beadle Lk Rd to 8 ½ Mile
Tree cleanup will continue at this location:

  • C Drive N, from Beadle Lk Rd to 8 ½ Mile
Week of September 28

The following roads have had paving completed and are awaiting restoration.

  • Belton
  • Fruin
  • Linn
  • Woodway
  • Pinewood
  • Pawnee
  • Cherokee
  • Marion
  • Auburn
  • L Drive N (Palmiter to Wheatfield)
  • Palmiter
  • N Princeton
  • Harper Creek Dr

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Bradford Subdivision
  • Lady Jessica Isle
  • Anway Drive
  • Fern Beach
  • Hollison Beach

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

Tree cleanup will continue at various locations

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

Week of September 21

 The following roads have had paving completed and are awaiting restoration.

  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Overton
  • S River
  • Silver Street
  • McCormick
  • Belton
  • Fruin
  • Linn
  • Woodway
  • Pawnee
  • Cherokee
  • Marion
  • Auburn

 The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton (W. lane)
  • Harper Creek Drive

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • D Drive N
  • Bradford Subdivision
  • Anway Drive
  • Lady Jessica Isle
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

The following roads will be milled in the coming days.

  • Fern Beach
  • Hollison Beach

Driveway removals may begin this week in these locations.

  • D Drive N
  • C Drive N

Tree cleanup will continue at various locations.

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

Week of September 14

The following roads have had paving completed and are awaiting restoration.

  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Overton
  • S River Ashley Ct
  • Silver Street
  • McCormick
  • Belton
  • Fruin
  • Linn
  • Woodway
  • Pawnee
  • Cherokee
  • Marion
  • Auburn

 The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton (W. lane)

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • D Drive N
  • Harper Creek Dr
  • Bradford Subdivision

 Driveway removals may begin this week in these locations.

  • D Drive N
  • Harper Creek Dr

 Tree cleanup will continue at various locations

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

 Week of September 8

The following roads have had paving completed and are awaiting restoration.

  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Overton
  • S River Ashley Ct
  • Silver Street
  • McCormick
  • Belton
  • Fruin
  • Linn
  • Woodway
  • Pawnee
  • Cherokee
  • Marion
  • Auburn

 The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton (W. lane)

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • D Drive N
  • Harper Creek Dr

Driveway removals may begin this week in these locations.

  • D Drive N
  • Harper Creek Dr

 Tree cleanup will continue at various locations.

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd


Week of August 31

The following roads have had paving completed and are awaiting restoration.

  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Easthill
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont
  • Boyer
  • Jono
  • 10 Mile Rd
  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Overton
  • S River Ashley Ct
  • Silver Street
  • McCormick

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St, Marion, Belton)

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Palmiter
  • L Drive N
  • Bradford/Rook Subdivision

The following roads will be pulverized/milled in the coming days.

  • Rook Ct. (milling)
  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd

Tree cleanup will continue at various locations.

  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

Week of August 24

The following roads have had paving completed and are awaiting restoration.

  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Easthill
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont
  • Boyer
  • Jono
  • 10 Mile Rd
  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Overton
  • S River Ashley Ct
  • Silver Street
  • McCormick

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St, Marion, Belton)

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Palmiter
  • L Drive N

 The following roads will be pulverized/milled in the coming days.

  • Bradford/Rook Subdivision

 Tree cleanup will continue at various locations.

  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd
  • C Drive N between 8 ½ Mile Rd and Beadle Lake Rd

Week of August 17

The following roads have had paving completed and are awaiting restoration.

  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Easthill
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont
  • Boyer
  • Jono
  • 10 Mile Rd
  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby
  • Overton
  • S. River Drive

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Ashley Ct
  • Silver Street
  • McCormick
  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St, Marion, Belton)

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • TBD

The following roads will be pulverized/milled in the coming days.

  • Palmiter
  • L Drive N

Driveway removals may begin this week in these locations.

  • Palmiter
  • L Drive N

Tree cleanup will continue at various locations.

  • Palmiter
  • L Drive N
  • D Drive N between 6 ½ Mile Rd and Beadle Lake Rd


Week of August 10

The following roads have had paving completed and are awaiting restoration.

  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Easthill
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont
  • Boyer
  • Jono
  • 10 Mile Rd
  • O’Neil
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Crosby

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Ashley Ct.
  • Overton
  • S River Drive

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Silver Street
  • McCormick
  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St, Marion, Belton)

 Tree cleanup will continue at various locations.

  • Palmiter
  • L Drive N


Week of August 3

The following roads have had paving completed and are awaiting restoration.

  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill and Maxwell)
  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Lowell
  • Easthill
  • Hidden Forest
  • Shadowood Sub
  • Winding Wood Sub
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont Boyer
  • Jono
  • 10 Mile Rd
  • O’Neil

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Crosby
  • Ashley Ct
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • Overton
  • S. River Drive

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Silver Street
  • McCormick
  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St, Marion, Belton)

Tree cleanup will continue at various locations.

Week of July 27

The following roads have had paving completed and are awaiting restoration.

  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill and Maxwell)
  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Lowell
  • Easthill
  • Hidden Forest
  • Shadowood Sub
  • Winding Wood Sub
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • Katherine
  • Olive St
  • Ruble
  • Beaumont
  • Boyer

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • N. Princeton
  • Crosby
  • Jono
  • Ashley Ct
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave
  • 10 Mile Rd

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Silver Street
  • O’Neil
  • Overton
  • Belton
  • Marion
  • McCormick
  • S River Drive

The following roads will be pulverized/milled in the coming days.

  • Fruin Sub (Woodway Ave, Pinewood Ave, Pawnee St, Linn Ave, Fruin Ave, Cherokee St, Auburn St)

Driveway removals will continue next week in these locations.

Tree cleanup will continue at various locations.

Week of July 20


The following roads have had paving completed and are awaiting restoration.

  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill and Maxwell)
  • Rosewood/Candlewood
  • H Drive N
  • I Drive N
  • Lowell
  • Easthill
  • Hidden Forest
  • Shadowood Sub
  • Winding Wood Sub
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck
  • White/W. Wallace
  • Herman/E. Wallace Sub
  • Vernon
  • 10 Mile Rd

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Princeton
  • Katherine
  • Olive St

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Beaumont
  • Crosby
  • Boye
  • Jono
  • Ashley Ct
  • Berrien Ave
  • Watts Street
  • Dexter St
  • S. Princeton St
  • Prospect Place
  • Interurban Ave
  • Clinton Ave
  • Crest Ave

The following roads will be pulverized/milled in the coming days.

  • Silver Street
  • McCormick
  • O’Neil
  • Overton
  • S. River Drive

Tree cleanup will continue at various locations.

Week of July 13

The following roads have had paving completed and are awaiting restoration.

  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill and Maxwell)
  • Rosewood/Candlewood
  • H Drive N
  • 11 ½ Mile
  • I Drive N
  • Lowell
  • Easthill
  • Hidden Forest
  • Shadowood Sub
  • Winding Wood Sub
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Princeton
  • Katherine
  • Olive St
  • Vernon
  • Herman/E. Wallace Sub

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • 10 Mile Rd
  • Beaumont
  • White/W. Wallace

The following roads will be pulverized/milled in the coming days.

  • Crosby
  • Boyer
  • Jono
  • Ashley Ct

Driveway removals will continue next week in these locations.

  • W. Wallace/White
  • Beaumont

Tree cleanup will continue at various locations.


Week of July 6


The following roads have had paving completed and are awaiting restoration.

  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill and Maxwell)
  • Rosewood/Candlewood
  • H Drive N
  • 11 ½ Mil
  • I Drive N
  • Lowell
  • Easthill
  • Hidden Forest
  • Shadowood Sub
  • Winding Wood Sub

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Princeton
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Peck

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Katherine
  • Olive S
  • Vernon
  • Herman/E. Wallace Sub

The following road will be pulverized/milled in the coming days.

  • 10 Mile Rd
  • Beaumont Drive

Driveway removals will continue next week in these locations.

  • Wallace St. E
  • Herman
  • Stone S
  • Elizabeth S
  • French S
  • Beaumont

Tree cleanup will continue along 10 Mile Rd.  All this work is weather dependant. 

Week of June 29

The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Pebble/Gavin Sub
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )
  • Rosewood
  • Rosebud Ct
  • H Drive N
  • 11 ½ Mile
  • I Drive N
  • Lowell

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Moonwood
  • Princeton
  • Easthill
  • Hidden Forest

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Peck
  • Katherine
    Olive S
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Vernon

The following road will be pulverized/milled in the coming days.

  • 10 Mile Rd
  • Herman/E. Wallace Sub
  • Beaumont Drive

Driveway removals will continue next week in these locations.

  • Wallace St. E
  • Herman
  • Stone S
  • Elizabeth S
  • French S
  • Beaumont

Tree cleanup will continue along 10 Mile Rd and contractors will be installing concrete curb at various intersections.

All of this work is weather dependent.

Week of June 22

The following roads have had paving completed and are awaiting restoration. 

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Thelma/Gregg Subdivision (Gregg and King) 
  • Keathley Subdivision (Keathley, Trickovic)
  • Sawyer & Strongwood Subdivision (Sawyer, Lowell, Grant and Strongwood)
  • L Drive N
  • 11 ½ Mile Rd
  • I Drive N

The following roads have had the base course of asphalt paved.  The top course will be paved in the coming days.

  • Lowell 200’
  • Moonwood 
  • Rosebud and Harperwood
  • H Drive N
  • Pebble/Gavin (Overlay)

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Brandywood
  • Shadowood Subdivision
  • Easthill Section
  • Katherine
  • Lourel 
  • Arlington
  • Palmer
  • Evanston
  • Vernon

The following roads will be pulverized/milled in the coming days.

  • Katherine
  • Olive
  • Peck 

Driveway removals will continue next week in these locations. 

  • Easthill Drive (West section of Easthill)
  • Katherine
  • Lourel 
  • Arlington
  • Palmer
  • Evanston
  • Vernon
  • Princeton

Tree cleanup will continue along I Drive N and 10 Mile Rd.

Contractors will be installing concrete curb at various intersections.

All work is weather dependent.  

Week of June 15

The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Thelma/Gregg Subdivision (Gregg and King)
  • Keathley Subdivision (Keathley, Trickovic)
  • Sawyer & Strongwood Subdivision (Sawyer, Lowell, Grant and Strongwood)

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Lowell 200’
  • Moonwood
  • L Drive N
  • 11 ½ Mile Rd
  • I Drive N

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Brandywood
  • H Drive N 
  • Shadowood Subdivision
  • Easthill West Section
  • Katherine
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Vernon

The following roads will be pulverized/milled in the coming days.

  • Katherine
  • Olive
  • Peck

Driveway removals will continue next week in these locations.

  • Easthill Drive (West section of Easthill)
  • Katherine
  • Lourel
  • Arlington
  • Palmer
  • Evanston
  • Vernon

Tree cleanup continues along I Drive N and 10 Mile Rd.  Contractors will be installing concrete curb at various intersections.

Week of June 8

The following roads have been paved and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Thelma/Gregg Subdivision (Gregg and King)
  • Keathley Subdivision (Keathley, Trickovic)
  • Sawyer & Strongwood Subdivision (Sawyer, Lowell, Grant and Strongwood)

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Lowell 200’
  • Moonwood
  • L Drive N
  • 11 ½ Mile Rd
  • I Drive N

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Brandywood
  • H Drive N 
  • Shadowood Subdivision

The following roads will be pulverized/milled in the coming days.

  • Easthill West Section
  • Katherine
  • Lourel
  • Arlington
  • Palmer
  • Evanston

Driveway removals will continue next week in these locations.

  • Easthill Drive (West section of Easthill)

Tree cleanup will continue along I Drive N and 10 Mile Rd.

Contractors will be installing concrete curb at various intersections.  

All work is weather dependant.  

Week of June 1

The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell)
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Thelma/Gregg Subdivision (Gregg and King)

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Sawyer & Strongwood Subdivision (Sawyer, Grant, Lowell, and Strongwood)
  • Thelma     
  • Keathley Subdivision (Keathley, Trickovic)
  • Moonwood     
  • L Drive N
  • 11 ½ Mile Rd

The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Brandywood
  • I Drive N
  • H  Drive N 

The following road will be pulverized/milled beginning Tuesday afternoon.

  • Shadowbend Subdivision 

Driveway removals will continue next week in these locations.

  • Easthill Drive (West section of Easthill)

Tree cleanup will continue along I Drive N and 10 Mile Rd.

Contractors will be installing concrete curb at various intersections along 10 Mile Rd, Keathley/Wattles Rd.

All work is weather dependant.  

Week of May 25

 The following roads have been paved and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell)
  • Dreamfield
  • Logans Run
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)

The following roads have received the base course of asphlat.  The top course will be paved in the coming days.

  • Sawyer & Strongwood Subdivision (Sawyer, Grant, Lowell, and Strongwood)
  • Thelma & Gregg Subdivision (Thelma, Gregg, King)
  • Keathley Subdivision (Keathley, Trickovic)
  • Moonwood

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Brandywood
  • I Drive N
  • 11 ½ Mile Rd

The following roads will be pulverized beginning Tuesday.

  • H Drive N
  • L Drive N between 12 Mile Rd and gravel section

Driveway removals will continue next week in these locations.

  • Easthill Drive (West section of Easthill)

Tree cleanup continues along I Drive N, 11 ½ Mile Rd and 10 Mile Rd.  Contractors will be installing concrete curbs at various intersections along 10 Mile Rd, Keathley/Wattles Rd.

Week of May
18


The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )
  • Dreamfield
  • Logans Run
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)

The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Sawyer & Strongwood Subdivision (Sawyer, Grant, Lowell, and Strongwood)
  • Thelma & Gregg  Subdivision (Thelma, Gregg, King)

 The following roads have been pulverized/milled and are in the process of being graded and compacted.  Paving is planned for the coming days.

  • Keathley Subdivision  (Keathley, Trickovic)
  • Moonwood and Brandywood
  • I Drive N

 The following road will be pulverized beginning Wednesday/Thursday.

  • 11 ½ Mile Rd

Driveway removals will continue next week in these locations.

  • Easthill Drive (West section of Easthill)

Tree cleanup will continue along I Drive N and removals and trimming will continue along 10 Mile Rd.
Contractors will be installing concrete curb at various intersections along 10 Mile Rd, Keathley/Wattles Rd.
All of this work is weather dependent.

Week of May 11

The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford, Brigden, Maxwell )


The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.

  • Dreamfield Dr
  • Logans Run
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Sawyer & Strongwood  Subdivision (Sawyer, Grant, Lowell, and Strongwood)

The following roads have been pulverized/milled and are in the process of being graded and compacted. Grading and compactions should be complete by the end of next week. Paving of the base course is expected to begin this week and continue throughout the following week.

  • Keathley Subdivision  (Keathley, Trickovic)
  • Thelma & Gregg  Subdivision (Thelma, Gregg, King) – paving Saturday
  • Winding Wood Subdivision  (Moonwood, Brandywood)

 The following road will be pulverized beginning Thursday.

  • I Dr N

 Driveway removals will continue next week in these locations.

 Tree cleanup will continue along I Dr N. Removals and trimming will continue along 10 Mile Rd and H Dr N. 

Contractors will continue installing leaching basins at various locations along 10 Mile, I Dr N and Keathley Subdivision this week.

All of this work is weather dependent.


Week of May 4
The following roads have had paving completed and are awaiting restoration.

  • Jane St
  • Eastfield Ct
  • Brigden Subdivision (Mill St, Kimball, Pickford)
The following roads have had the base course of asphalt paved. The top course will be paved in the coming days.
  • Dreamfield Dr
  • Logans Run
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Bridgen Subdivision (Maxwell, Bridgen)
  • Niblett & Fifer Subdivision (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
The following roads have been pulverized and are in the process of being graded and compacted. Grading and compactions should be complete by the end of next week. Paving of the base course is expected to start Monday and continue throughout the week.
  • Sawyer and Strongwood Subdivision (Sawyer Ave, Lowell, Ave, Grant Ter, and Strongwood Ave) 
The following roads will be pulverized beginning Tuesday.
  • Keathley Subdivision (Keathley, Trickovic)
  • Thelma & Gregg Subdivision (Thelma, Gregg, King)
  • Easthill Dr (Non-curbed portion)
Driveway removals will continue next week in these locations.

Tree cleanup will continue along I Dr N. Removals and trimming will continue along 10 Mile Rd and H Dr N.

Contractors will continue installing leaching basins at various locations along 10 Mile Road this week.

All of this work is weather dependent.

Week of April 27
The following roads have had the base course of asphalt paved. The top course will be paved next week as long as the weather cooperates.
  • Dreamfield Dr
  • Logans Run
  • Eastfield Ct
The following roads have been pulverized and are in the process of being graded and compacted. Grading and compactions should be complete by the end of next week. Paving of the base course is expected to start Monday and continue throughout the week.
  • Jane St
  • Brigden Subdivision (Kimball Ave, Maxwell Ave, Mill Rd, Pickford Ave, and Brigden Dr)
  • Niblett and Fifer Subdivision. (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Sawyer and Strongwood Subdivision (Sawyer Ave, Lowell, Ave, Grant Ter, and Strongwood Ave)
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
Driveway removals will continue next week in these locations.
 
Tree cleanup will continue along I Dr N. Removals and trimming will begin along 10 Mile Rd and H Dr N.
 
Contractors will begin installing leaching basins at various locations along 10 Mile Road next week.
 
No new roads are expected to be pulverized next week. Pulverizing should resume the week of May 4th in the Thelma & Gregg subdivision and the Keathley subdivision.

All of this work is weather dependent.

Week of April 20

Construction is moving ahead very quickly. The following roads have been pulverized:
  • Dreamfield Dr
  • Logans Run
  • Eastfield Ct
  • Jane St
  • Stockyards Area (Dick St, La Grange Ave, and Raymond Rd N)
  • Brigden Subdivision (Kimball Ave, Maxwell Ave, Mill Rd, Pickford Ave, and a portion of Brigden Dr)
Driveway removals and road grading will continue next week in these locations.
 
The following roads will be pulverized next week:
  • Niblett and Fifer Subdivision. (Alexander Ave, Fifer Ln, French Ln N, N Elizabeth St, Niblett St, and Stone Ave N)
  • Sawyer and Strongwood Subdivision (Sawyer Ave, Lowell, Ave, Grant Ter, and Strongwood Ave). Could be moved to the following week depending on contractor schedule. 
Paving has tentatively been scheduled to start Wednesday. This could be moved as Lakeland fine tunes operations at their plant during this first week of production. Roads that could have their first course of asphalt paved are as follows:
  • Dreamfield
  • Logans Run
  • Eastfield Ct.
Tree trimming and removals will begin Monday and continue throughout the week on the following roads.
  • 10 Mile
  • I Dr N
  • Thelma and Gregg Subdivision.
Additional roads could be added depending on production and weather. All of this work is weather dependent.
 
Week of April 13
Emmett Township road work will be starting next week!
Beginning Tuesday, April 14th Hoffman Bros. will begin cutting driveways in the following subdivisions/roads in this order:
  • Dreamfield
  • Logan’s Run
  • Eastfield Ct
  • Jane St
  • Stockyards Area (Raymond Rd, Dick St, and La Grange Ave)
  • Brigden Subdivision. (Brigden Dr, Pickford Ave, Kimball Ave, Maxwell Ave, and Mill Rd)
  • Niblett Street
  • Alexander Ave
  • N Stone Street
  • N Elizabeth Street
  • N French Lane 
  • Fifer Lane
  • Sawyer Ave
  • Strongwood Ave
  • Lowell Ave
  • Thelma Dr
  • Gregg Rd
  • Kings Ln
  • Keathley Dr
  • Trickovic Ln
  • East Hill Drive
  • Shadowood Ln
  • Harperwood Drive
  • Brandy Wood Ln
  • Moonwood Trail
  • Winding Wood Way
  • Shadow Bend Lane
  • Candlewood Ln
  • Rosewood Trail
  • Rosebud Ct

Beginning Thursday, April 16th, JL Milling will begin pulverizing the above subdivision/roads in the same order.