Click here for an interactive map of the Emmett Township Local Road Project
2022 construction overview:
Read the press release
PROJECT UPDATE MAY 13, 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 5, 2022:
The following streets have been paved with a base layer of HMA:
- Powell
- Hammond, N of Westbrook
- Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
Trenching has begun on 6 mile rd with pulverization to follow, likely next week.
Christian and Ryan’s Run will be milled today ,5/5, after being rescheduled from this past Tuesday.
PROJECT UPDATE APRIL 28, 2022:The following streets have been paved with a base layer of HMA:
- Juanita, from E Drive N to End
- Tower Rd
- Westbrook
- Powell
- Hammond, N of Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, from 6.5 Mile – End
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
The following streets are scheduled to be pulverized/milled Tuesday, 5/3/22:
- Christian Drive/Ryan’s Run (Mill 1.5”)
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 21, 2022:The following streets have been paved with a base layer of HMA:
- Juanita
- Orbit
- Westbrook
- Powell
- Hammond, N of Westbrook
The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Tower Rd
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
The following streets are scheduled to be pulverized this Thurs/Fri:
- Bach/Hoover/Embury
- 6.5 Mile Rd
The following streets were striped with pavement markings on Wednesday:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 14, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- Tower Rd
- Eisenhower (Milled)
The following streets are scheduled to be pulverized this Thurs/Fri:
- President Streets Subdivision
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings next week:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 7, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
The following streets are scheduled to be pulverized next Thurs/Fri:
- President Streets Subdivision
- Tower Rd
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings on April 14th:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 5, 2022:The following streets have had driveways cut and berm graded and are currently being pulverized this week, April 5 (Mon-Wed):
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- President Streets Subdivision
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
On April 14, the following streets are scheduled to be striped with pavement markings:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
PROJECT UPDATE MARCH 28, 2022:
To prepare for pulverizations that will begin on April 4, contractors have begun cutting driveways and deberming (scraping the grass/organic material away from the edge of the road).
Starting on April 4, E Drive N will be pulverized between 6 ½ Mile Rd. and Beadle Lake Road.
After E Drive N is pulverized, Westbrook (off of Raymond Rd) will be pulverized, and then the Presidents Streets (Eisenhower, Nixon, Eastland, Dulles, Humphrey, McArthur, Knowland).